The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____. a. forward pass b. backward pass c. fast tracking d. free slack

Answer :

Ritmeks

Answer:

Free slack

Explanation:

Free slack can be defined as the amount of time an activity may be delayed without delaying a succeeding activity or a project finish time.

Free slack gives resilience in project management. When leveraged in the right way, project managers can shift activities and resources to meet the project objectives. It is the amount of time an activity can be delayed without impacting other activities or the project end date and changes during the period of the project accomplishment.

The amount of time that can be delayed without delaying the early start date of an immediate activity is known as Free Slack.

The correct answer is:

Option D. Free slack.

Free slack can be defined as:

1. Free slack refers to the amount of time an activity requires that can be delayed without delaying the activity of the succeeding project's deadline.

2. It provides resilience in the management of projects and activities.

3. The managers and leads can shift the activities to meet the objective of the activity or project. It is the amount of time delayed without impacting the other activities' deadline.

Thus, the correct answer is free slack.

To know more about free slack, refer to the following link: